During their recent regular meeting the Sheridan County Commission approved a change order request from Dick Anderson Construction on the remodel project at the Sheridan County Sheriff’s Office.
The change order was requested to reflect needed additional insulation and an additional card reader to be added to the project.
According to the change order, additional exterior rigid and sheathed insulation will add an additional $4,200.56 to the project; and the additional card reader will add $294.01 for a total additional cost of $4,494.56.
The change order will also add three days to the schedule for the project.