WYDOT Update on Buffalo Main Street Project for July 17

July 18, 2025

News – Sheridan Media

The Wyoming Department of Transportation (WYDOT) issued the latest update on the Buffalo Main Street project as of Thursday, July 17.

On South Main Street from the Bypass Road to Interstate 25, paving of the wearing course is expected to begin on Friday, July 18.

Expect lane closures, a pilot car, and flagging operations.

On South Main Street from Angus Street to Brock Street, paving of the wearing course resumed on July 17.

Downtown Main Street at the Clear Creek Bridge, contractors will be pouring an epoxy overlay on the bridge on Monday, July 21 and Tuesday, July 22.

The work will require a lane closure and sidewalk closure to complete.

Watch for flagging operations.

On North Main Street from Fort Street to Foote Street, the contractor will be connecting the final service lines this week and will begin back-filling at these locations.

And finally, contractors will be working on the Cemetery Creek Culvert and on North Main Street on Saturday, July 19.